Looking Up River… and Beyond: Over the years, the Trinity River has meant many things to the citizens of Fort Worth
– prosperity, beauty, recreation, and at times, even tragedy. Visit these major events leading up to the grand vision we have for our Trinity River today.

...
1849

United States Army Major Ripley Arnold establishes Fort Worth.

...
1908

Heavy rainfall causes flooding of the West Fork of the Trinity River. Five people died, over 4,000 were left homeless and damage exceeded $2.5 million.

...
1914

The first reinforced concrete arch bridge in the United States to use self-supporting reinforcing steel. The Paddock Viaduct was constructed across the Trinity River just north of the courthouse.

...
1922

The Trinity River rose to cover 3,000 acres, killing 37 people and destroying many more businesses and homes. The existing levees, which were constructed after the 1908 flood, did not prevent damage, so they were increased in height.

...
1942

This flood ripped through Fort Worth’s near northside causing damaging results to the area, including East Exchange Avenue (commonly known as The Stockyards).

...
1949

North Central Texas was inundated with torrents of rain in the upper Trinity River. Neighborhoods surrounding downtown were flooded by more than 10 feet of water. Thousands were left homeless, 10 people died and property damages reached $15 million.

...
1949

The United States Army Corps of Engineers opened a Fort Worth office and began building a flood protection system on the Trinity that included the present system.

...
1957

The Federally funded improvements were completed, including the construction and strengthening of the levees. The plan also straightened the Clear Fork and West Fork of the river, removing the natural meander of the river in favor of a channel system. Thousands of trees along the banks were bulldozed and levees became barriers that kept people away from the river.

...
1969

As a result of the levee project, the Trinity River was left a dry, littered ditch for most of the 50s, 60s and early 70s.

...
1971

Local citizen’s group formalized as Streams and Valleys, an organization charged with the beautification and recreational development of the Trinity River and its tributaries.

...
1971

The “Halprin Plan” was developed to provide low-level dams, extensive multi-user trail systems, lighting, planting thousands of trees and vastly improving public areas.

...
1988

EDAW, a noted urban planning firm from Alexandria, Virginia, was commissioned to develop a new plan that focused on expanding public access to the river.

...
1989

Nearly 40 years to the day after the devastating flood of 1949, another severe flood rippled through the area killing four and devastating the entire Metroplex.

...
2002

The Trinity River Master Plan was designed to provide flood protection, recreation, scenic beauty and accessibility to the public.

...
2006

The TRVA was formed to coordinate the project schedule based on local partnerships with the City of Fort Worth, Tarrant County, Streams and Valleys and the Tarrant Regional Water District, working closely with the United States Army Corps of Engineers and the Texas Department of Transportation.

...
2006

Tarrant Regional Water District (TRWD) Neighborhood Recreation Enhancement Plan was adopted for the entire Trinity Trail system.

...
2008

The City of Fort Worth recommended adding Gateway Park to the project bringing needed flood protection (valley storage) and park amenities to the over 1,000 acre park on the east side of Fort Worth.

...
2014

The Texas Department of Transportation’s (TxDOT) contractor broke ground on the three signature v-pier TxDOT bridges, marking the first major phase of infrastructure construction related to the project.

...
2016

Congress passed the Water Infrastructure Improvements for the Nation Act (WIIN), which included the Water Resources Development Act of 2016. This bill fully authorized the Central City Flood Control Project.

...
2019

USACE completed valley storage excavation in Riverside Park. Removing roughly 225,000 cubic yards of material in the park will provide needed flood protection and allow the City of Fort Worth to add park amenities benefiting the communities east of Downtown.

...
2019

USACE completed the first phase of valley storage excavation in Gateway Park. This $28.5 million contract, from USACE, removed over 1.4 million cubic yards of material (enough material to fill roughly 40% of AT&T Stadium) adding needed flood protection for Fort Worth.

...
2019

With a majority of the front end local work completed, TRVA was restructured and now performs an advisory role to the City of Fort Worth and TRWD.

...
2020

USACE completed the excavation of the second phase of valley storage work in Gateway Park. USACE has now removed roughly 1.7 million cubic yards of material in the park creating essential flood control for Fort Worth.

...
2021

The Texas Department of Transportation’s (TxDOT) contractor opened all three Panther Island Signature V-Pier Bridges to the public. These three bridges are located on Henderson Street, North Main and White Settlement. Before USACE can begin the bypass channel, these bridges were being built in a dry condition to maintain access in the area throughout the duration of the project.

...
2022

The Central City Flood Project received $403 million in funding from the U.S. Army Corps of Engineers (USACE). This funding will allow USACE to complete the final design of all project components and construction of the bypass channel.

Panther Island / Central City

Project Studies

Fort Worth’s tremendous population growth issue, which led to our outgrowing of the current levee system, was identified back in the mid-1980’s. Our current levee system was built for a population of roughly 350,000 people and Fort Worth has now surpassed 900,000 people. Initially, there were 16 studies completed that led to the US Army Corps of Engineers Central City Flood Control Project, with an additional 7 studies to follow once the project was authorized.

Mid-1980s: Growing concern about flooding due to population growth

There was general understanding that flood hazards had already increased during the years subsequent to construction of the floodway system in the 1950s and that the level of flood protection in the regional system had deteriorated. Responding to that concern nine municipalities, three counties and TRWD petitioned Congress for a new study authority to examine the issue.


April 22, 1988: U.S. Senate Committee on Environment & Public Works Resolution

In response to the request, Senate EPW authorized USACE to investigate the potential flooding problems and opportunities in the Upper Trinity River Basin to provide improvements in the interest of flood protection, environmental enhancement, water quality, recreation, and other allied purposes.


Fall 1988: Trinity River and Tributaries Environmental Impact Statement

With Senate authorization, the Trinity River and Tributaries Environmental Impact Statement (TREIS) was prepared by USACE to address the increase in floodplain development that was occurring in the Upper Trinity River basin. The TREIS raised awareness that a large area of floodplain lands within the Upper Trinity River Basin could be developed outside the jurisdiction of the USACE which would cause increases in flooding frequency to adjacent and downstream areas. This awareness led to one of the main conclusions of the TREIS planning efforts, existing regional floodplain management policies were inadequate to maintain existing levels of flood protection within the region’s major urban areas. Development in areas outside USACE jurisdiction will further increase flooding frequency.


1988-1990: Development of the Corridor Development Certificate Process

In response to the TREIS finding for greater floodplain management policies to limit the continued increases in flooding frequencies, the Corridor Development Certificate (CDC) program was initiated. It is a joint effort of the NCTCOG, the USACE, and member NCTCOG cities and counties with jurisdiction over the Trinity River floodplain. It investigates the adjacent and downstream impacts of site-specific impacts.


March 1990: Upper Trinity River Basin, Trinity River, Texas — Reconnaissance Report

The TREIS and CDC heightened regional awareness relative to flood hazards. The study affirmed that urban development had exceeded previously projected expectations causing increased runoff and peak discharges. The process generated broad recognition that flood hazard could (and would) deteriorate in the future. The report also found that while adherence to the CDC and the mitigation outlined in the TREIS could stabilize the existing flooding situation, following these guidelines would not restore the level of protection that had been lost in the decades between the l950s and the 1980s. Eleven flood control concepts were identified for future studies.


August 1990: USACE/NCTCOG Upper Trinity River Regional Feasibility Study

Following the Reconnaissance Report, USACE and the North Central Texas Council of Governments (NCTCOG), acting as local sponsor for the original 13 concerned governments, executed a Feasibility Study Cost Sharing agreement to conduct joint investigations into water resource problems. The original intent of the Feasibility Study was to conduct more rigorous investigations of the flood control concepts preliminarily identified in the Reconnaissance Report. This same agreement has provided the operating framework for a number of site-specific investigations of flood control projects throughout the region, of which the Central City project investigation later became one.


1995: USACE Upper Trinity River Basin, Texas Information Paper, “A Benefit-Cost Analysis”

In 1995, an “information paper” was issued by USACE containing the study results of the flood control concepts that were identified in the Reconnaissance Report to date. Some 88 feasible multi-purpose measures were identified and evaluated. Of particular significance was a finding that a detention structure on the West Fork in Wise County would mitigate flood hazards in Tarrant County; however, the citizens in Wise County strenuously objected to further study of the concept, local sponsorship faded and the Boyd Detention Structure in Wise County died by 1999.


1999: Streams & Valleys “Tilley Plan”

The intense public dialog surrounding preparation and release of the Information Paper generated additional planning activity at the local level in Fort Worth. Streams & Valleys, an independent non-profit, initiated a broad scale community-based effort to develop a Master Plan for the river in Tarrant County. This plan, completed in 1999, was often referred to as the “Tilley Plan.” The Master Plan focused on recreation-oriented improvements; however, the plan recognized the flood protection function of the Trinity River Floodway System. As TRWD began to implement portions of the Tilley Plan, focus shifted back to the USACE and the opportunities identified in the Information Paper because there was a high degree of compatibility between many of the initiatives identified in the Information Paper and the Tilley Plan.


1999: Clear Fork/West Fork Interim Feasibility Study

USACE and TRWD entered into a cost-sharing agreement, conducted under the umbrella of the 1990 Upper Trinity River Feasibility Study, to prepare a comprehensive study of the Clear Fork and West Fork of the Trinity River in Fort Worth. TRWD entered into this cost-sharing agreement as a subset to the umbrella agreement because this body of work was for the investigation of a specific area with the Upper Trinity River Regional Area which would not have impacted that other parties to the original umbrella study of the region. Early scoping of the cost-shared Clear Fork/West Fork Interim Feasibility Study identified nine river segments having numerous opportunities for flood damage restoration and ecosystem restoration. Of particular interest was flooding and annual damages in the study area associated with the sump system for the Fort Worth Floodway. Several alternatives, including buyout programs and excavation to increase sump capacity were preliminarily evaluated, but no measures were found to be economically viable under the USACE Federal criteria.


June 2000: USACE Upper Trinity River Basin – Final Programmatic Environmental Impact Statement

During the same period that TRWD and USACE were working on the Clear Fork/West Fork Feasibility Study, the Fort Worth District of the USACE was in the process of: completing a feasibility study on a flood control project along Johnson Creek in Arlington, initiating interim feasibility studies for Trinity River projects in Dallas, and initiating another interim feasibility study with TRWD on the Riverside Oxbow Project in Fort Worth.

Because of the wide variety of initiatives being studied under the Clear/ West Fork Interim Feasibility Study, the USACE concluded that adequate evaluation of the cumulative impacts of these projects required a programmatic environmental evaluation. The National Environmental Policy Act of 1969 (NEPA) requires Federal agencies to fully document and evaluate the cumulative impacts of proposals, as well as the direct and indirect impacts. Accordingly, concurrent with the USACE/TRWD Clear Fork/West Fork Interim Feasibility Study, work was initiated on the USACE Upper Trinity River – Final Programmatic Environmental Impact Statement.

Most importantly, this EIS set the stage for focused evaluation of discreet segments of the river (such as the Central City Segment) for flood damage reduction, ecosystem restoration, and recreation purposes.


2001-2003: Streams &Valleys, City of Fort Worth, TRWD – Trinity River Vision Master Plan

Jointly, local Fort Worth agencies and organizations undertook the creation of a new Master Plan for the river, titled “Trinity River Master Plan.” The purpose of the plan was to create a vision that would combine stormwater runoff, flood control and improved quality of life enhancements. The community-input process consisted of over 200 public meetings. In October 2001, the input was provided to several urban planning and hydraulic experts in a two-day public workshop that focused on the central city area of the Clear Fork and West Fork. The experts evaluated the community input and the condition of the current levees. The outside experts proposed the same plan that solved San Antonio’s flood challenges, a bypass channel and flood gates. Workshop participants believed the bypass channel concept could meet all of the community’s goals. The Master Plan was adopted by the City of Fort Worth, Tarrant County and TRWD in 2003.


April 2003: Trinity River Floodway Channel Realignment Study

With the ability to focus on discreet segments of the river for flood damage reduction, and the community’s desire to pursue the viability of a bypass channel to resolve Fort Worth’s deteriorating level of flood protection, the technical feasibility of a bypass channel approach was explored. The technical companion engineering study was titled, Trinity River Vision: Evaluation of the Trinity River Floodway Channel Realignment. This study was funded by TRWD and a Texas Water Development Board grant.


May 2003: Riverside Oxbow Feasibility Study

The USACE flood project from the early 1960’s left the Riverside Area in a challenged state. The area flooded regularly but when not inundated the area had little viability. The early flood management effort stripped the area of most of the indigenous environment. The Riverside Study was to restore the condition that early flood management efforts had left behind. USACE technical evaluation and cost review studies led to the recommendation to move forward with federal efforts having received Approval by USACE Chief of Engineers. Project did not move forward for lack of support by OMB.


2003 – 2004: Central City Interim Feasibility Study

The community’s Trinity River Vision Master Plan for the river and the companion engineering study, Evaluation of the Trinity River Floodway Channel Alignment required focused resources and attention on the Central City segment of the Trinity River. To accomplish this effort, in May 2004, the USACE and TRWD agreed to modify the Project Management Plan for the West Fork/Clear Fork Interim Feasibility Study to focus exclusively on problems and opportunities in this river reach. Analysis from the Clear Fork / West Fork Interim Feasibility Study indicated that 86% of the Fort Worth levee system no longer provided the level of protection that is was designed to deliver – and Fort Worth had nearly doubled in size since the levees were designed.


2004-2006: USACE Upper Trinity River Central City Environmental Impact Statement

Many prior studies had identified decades of deteriorating flooding conditions, enormous population growth contributing to increased flooding frequency and an understanding that 86% of the levees in Fort Worth were no longer adequate to protect the community. With that information, Congress authorized USACE to conduct the Environmental Impact Statement for the Central City Project to determine if there was technically sound and environmentally acceptable solution according to USACE criteria.


February 2005: USACE Economic & Fiscal Impacts Study of Central City Project

USACE hires University of North Texas, Economic Research Department, to conduct an economic analysis of the Central City project to determine the economic and fiscal impacts of the project as part of the USACE Environmental Impact Study for Central City.


April 2006: USACE Record of Decision for Central City Project

During the EIS evaluation, USACE investigated three alternatives to Fort Worth’s outdated levee system: no changes, raise the levees, or the introduction of a bypass channel option. No changes just accepted the given risk which failed to solve the issue. Raising the levees increased both the height and width of the levees. The expanded levee footprint required the taking of a disproportionately large footprint of the properties that the study was trying to protect thereby making the costs of the project disproportionate to the benefits. The channel provided the greatest benefits with the least negative impacts. The channel restores protection to over 2,400 acres of neighborhoods at a cost of $435 million.


June 2006-2008: USACE Modified Central City Supplemental Environmental Impact Study

At the request of the City of Fort Worth, USACE evaluates the benefits and costs of merging the USACE Central City Project and another local USACE project, Riverside Oxbow. The City asked for the study because previous flood management efforts stripped the area of its indigenous qualities. The City of Fort Worth hoped that the area could be repurposed to better handle both flood waters and deliver the original ecosystem restoration goals that was the main purpose of the original Riverside Oxbow project. To assure a comprehensive analysis the total hydraulic system including the Central City and Riverside Oxbow areas and the channels upstream and downstream of these areas was evaluated.


May 2008: USACE Independent Technical Review (ITR)

Supplemental EIS process requires an independent review by another USACE District that has no knowledge of the Modified Central City Project. The outside technical review is a peer review that examines the data, findings and recommendations to affirm whether the flood challenges have been addressed and if there are any ways to mitigate (lessen) impacts of the project to be constructed.


May 2008: USACE Independent Cost Review (ICR)

Walla Walla, USACE, is the USACE Project Center for Excellence which performs all USACE ICRs for in the country. The ICR was required as part of the Supplemental EIS. Walla Walls performs independent cost reviews of all project cost estimates for the Modified Central City Project.


2008: USACE Record of Decision for Modified Central City Flood Control Project

During the EIS evaluation, USACE determined merging the previously authorized Central City Project with the previously federally recommended Riverside Oxbow Project provided greater outputs and execution efficiencies. Merging the two benefitted Central City because the original Central City Project required the acquisition of a great amount of private property to convert to flood needs. Merging Riverside mitigated that element because the flood needs could be handled using previously owned public property in Riverside Oxbow area that was already being used for flood purposes. Riverside Oxbow Project benefitted because the primary goal of that project was ecosystem restoration. Riverside Oxbow Project gained by merging because Central City is planting indigenous trees in the area to manage the Central City flood needs. The trees slow the water down providing both flood protection and the original Riverside Oxbow need, ecosystem restoration. The cost of the now Modified Central City Project incorporating the Riverside Oxbow Project literally doubled the scope of the original Central City Project. With a project size that doubled, respective costs to complete ran relative. The Modified Central City Cost with expanded scope are reported to be$810 million.


November 2014: UNT Economic Benefit Analysis of Modified Central City Project Which Incorporates Federally Recommended Riverside Oxbow Project

With expanded scope and respective costs, all local partners had to put together a finance plan to cover additional local obligations. As part of that effort, TRWD reached out to the same UNT team that did the first Economic Analysis for USACE to get an updated study of financial benefits to help local partners put together a financing plan covering local costs.


December 2016: Full Congressional Authorization of USACE Modified Central City Project

Congress fully authorized USACE Modified Central City Flood Control Project which rolls the previously federally recommended Riverside Oxbow Project under the Central City Project name. Details: $810 project. Standard cost-share for flood and ecosystem components. Federal share for recreation component capped at 5.5 million (as opposed to standard 50/50 recreation split.)


August 2018: Local Benefit-Cost Risk Analysis Study for WIIN Act Request

Water Infrastructure Improvements for the Nation Act. Local partners use USACE defined footprint of at-risk properties that are no longer protected due to aging levee system. All value data was downloaded from the Tarrant Appraisal District to identify the value of the area at risk. TAD data in 2018 established that the value of the area at that time was already exceeding 2.3 billion with a flood control project cost of $810 million.


Panther Island / Central City

Project Awards & Praise

The comprehensive planning effort put together by the project partners has been gaining the attention in the areas of public planning, design and contracting. Below are some of the awards received by the project team.

2016 Regional Hispanic Contractor’s Association Pillar Awards
2014 Asian American Contractor’s Association
2011 U.S. Army Corps of Engineers
2009 American Institute of Architects (AIA) Fort Worth Chapter
2009 Fort Worth Metropolitan Black Chamber of Commerce-Minority Women Business Enterprise Excellence Award
2007 Fort Worth Hispanic Chamber of Commerce
2007 North Central Texas Council of Governments Center of Development Excellence
2007 Texas Chapter of the American Planning Association
2006 Midwest Section of the Texas Chapter of the American Planning Association
2005 Texas Society of Architects
2005 Boston Society of Landscape Architects
2005 The Waterfront Center – Excellence on the Waterfront
2003 North Central Texas Council of Governments Center of Development Excellence

Panther Island / Central City

Quarterly Construction Update

The Panther Island/Central City Flood Project is a multi-agency collaboration between the Tarrant Regional Water District, US Army Corps of Engineers, the City of Fort Worth and Tarrant County. The project was started in 2004 and expanded in 2009 (adding the Gateway Park flood water retention and recreation corridor). The key component is a 1.5-mile-long rerouting of the river just north of the Tarrant County Courthouse. When completed, the Panther Island/Central City Flood Project will deliver flood protection, environmental clean up of the Trinity River corridor, and recreation for more than 3,000 acres of Tarrant County land.

Panther Island / Central City

Presentation Info & Slide Decks

We provide group presentations to inform the community about the projects history, as well as current project status, with graphics and video. Recent presentations are listed below as a resource. If your group is interested in receiving a presentation, please click the following link to request one. Request a Presentation