With the official ribbon cutting ceremony taking place on the White Settlement Rd Bridge last weekend you might be asking yourself, what’s next?
White Settlement Rd. Bridge:
- Bridge opened to vehicle traffic on April 2nd
- Ribbon Cutting Ceremony took place on May 22nd
- The contractor continues to work on the underside of the bridge rubbing out concrete blemishes. The bottom of the bridge will be painted this summer
- Site grading is currently underway
North Main St. Bridge: Estimated Bridge Opening Summer
- The pedestrian traffic barrier has been completed
- The contractor has also completed the sidewalk and landscaping around the bridge
- The pedestrian sidewalk handrail is underway
Henderson St. Bridge: Estimated Bridge Opening Late Summer
- The final bridge deck was poured on May 5th
- Two abutment slabs were poured on May 12th and May 13th
- Currently the contractor is working on transverse tendon installation, stressing and grouting
- Simultaneously the falsework removal is underway
Posted | Filed Under: Newsroom